Utilizing Flexibility Services from a Large Heat Pump to Postpone Grid Reinforcement

    • Technical University of Denmark

    Research output: Chapter in Book/Report/Conference proceeding › Article in proceedings › Research › peer-review

    Abstract

    Distribution grid reinforcement problem is considered in this paper. Annual growth of the electric loads may lead to the congestion situations in the distribution network, where current flowing through components exceed their maximum current carrying capacity (MCCC). A conventional solution is to reinforce overloaded components, i.e. to replace it with the one with higher capacity. However, this will lead to the additional investments for the distribution system operator (DSO). An alternative solution is to utilize flexibility services (FS) such as reconfiguration (RE) and demand response (DR) to provide peak reduction from the large controllable loads (e.g. a heat pump) in the system. Several forecasts of the future load growth simulated in the MATPOWER are used to study the proposed solutions and identify their feasibility. The results show that both FS can be used to defer grid reinforcement providing economic benefits for the DSO.
    Original languageEnglish
    Title of host publication2018 IEEE Student Conference on Electric Machines and Systems
    Number of pages6
    PublisherIEEE
    Publication date2018
    Pages1-6
    ISBN (Electronic)978-1-5386-7348-5
    DOIs
    Publication statusPublished - 2018
    Event2018 IEEE Student Conference on Electric Machines and Systems - Huzhou, China
    Duration: 14 Dec 2018 → 16 Dec 2018
    https://ieeexplore.ieee.org/xpl/conhome/8611002/proceeding

    Conference

    Conference2018 IEEE Student Conference on Electric Machines and Systems
    Country/TerritoryChina
    CityHuzhou
    Period14/12/2018 → 16/12/2018
    Internet address

    Keywords

    • Distribution planning
    • flexibility service
    • heat pump
    • reinforcement
    • MATPOWER

    Fingerprint

    Dive into the research topics of 'Utilizing Flexibility Services from a Large Heat Pump to Postpone Grid Reinforcement'. Together they form a unique fingerprint.

    Cite this