Site calibration

Research output: Book/ReportReportResearch

Abstract

The report describes site calibration measurements carried out on a site in Denmark. The measurements are carried out in accordance to Ref. [1].
The site calibration is carried out before a power performance measurement on a given turbine to clarify the influence from the terrain on the ratio between the wind speed at the center of the turbine hub and at the met mast. The wind speed at the turbine is measured by a temporary mast placed at the foundation for the turbine. The site and measurement equipment is detailed described in [2].
The possible measurement sector for power performance according to [1] is also described in [2] and no results from the site calibration have shown any necessary exclusion from this sector.
All parts of the sensors and the measurement system have been installed by DTU.
Original languageEnglish
PublisherDTU Wind Energy
Number of pages66
Publication statusPublished - 2015
SeriesDTU Wind Energy WTT I
Number1135(EN)

Bibliographical note

This is an internal report and therefore not available in full text. Please contact author's or director of author's department for further information.

Keywords

  • DTU Wind Energy WTT I-1135(EN)
  • WTT-I-1135
  • WTT-I-1135(EN)

Cite this

Gómez Arranz, P., & Georgieva Yankova, G. (2015). Site calibration. DTU Wind Energy. DTU Wind Energy WTT I, No. 1135(EN)
Gómez Arranz, Paula ; Georgieva Yankova, Ginka. / Site calibration. DTU Wind Energy, 2015. 66 p. (DTU Wind Energy WTT I; No. 1135(EN)).
@book{ff167a5ee83b40c5a13b2232b7da9b74,
title = "Site calibration",
abstract = "The report describes site calibration measurements carried out on a site in Denmark. The measurements are carried out in accordance to Ref. [1].The site calibration is carried out before a power performance measurement on a given turbine to clarify the influence from the terrain on the ratio between the wind speed at the center of the turbine hub and at the met mast. The wind speed at the turbine is measured by a temporary mast placed at the foundation for the turbine. The site and measurement equipment is detailed described in [2].The possible measurement sector for power performance according to [1] is also described in [2] and no results from the site calibration have shown any necessary exclusion from this sector.All parts of the sensors and the measurement system have been installed by DTU.",
keywords = "DTU Wind Energy WTT I-1135(EN), WTT-I-1135, WTT-I-1135(EN)",
author = "{G{\'o}mez Arranz}, Paula and {Georgieva Yankova}, Ginka",
note = "This is an internal report and therefore not available in full text. Please contact author's or director of author's department for further information.",
year = "2015",
language = "English",
publisher = "DTU Wind Energy",
address = "Denmark",

}

Gómez Arranz, P & Georgieva Yankova, G 2015, Site calibration. DTU Wind Energy WTT I, no. 1135(EN), DTU Wind Energy.

Site calibration. / Gómez Arranz, Paula; Georgieva Yankova, Ginka.

DTU Wind Energy, 2015. 66 p. (DTU Wind Energy WTT I; No. 1135(EN)).

Research output: Book/ReportReportResearch

TY - RPRT

T1 - Site calibration

AU - Gómez Arranz, Paula

AU - Georgieva Yankova, Ginka

N1 - This is an internal report and therefore not available in full text. Please contact author's or director of author's department for further information.

PY - 2015

Y1 - 2015

N2 - The report describes site calibration measurements carried out on a site in Denmark. The measurements are carried out in accordance to Ref. [1].The site calibration is carried out before a power performance measurement on a given turbine to clarify the influence from the terrain on the ratio between the wind speed at the center of the turbine hub and at the met mast. The wind speed at the turbine is measured by a temporary mast placed at the foundation for the turbine. The site and measurement equipment is detailed described in [2].The possible measurement sector for power performance according to [1] is also described in [2] and no results from the site calibration have shown any necessary exclusion from this sector.All parts of the sensors and the measurement system have been installed by DTU.

AB - The report describes site calibration measurements carried out on a site in Denmark. The measurements are carried out in accordance to Ref. [1].The site calibration is carried out before a power performance measurement on a given turbine to clarify the influence from the terrain on the ratio between the wind speed at the center of the turbine hub and at the met mast. The wind speed at the turbine is measured by a temporary mast placed at the foundation for the turbine. The site and measurement equipment is detailed described in [2].The possible measurement sector for power performance according to [1] is also described in [2] and no results from the site calibration have shown any necessary exclusion from this sector.All parts of the sensors and the measurement system have been installed by DTU.

KW - DTU Wind Energy WTT I-1135(EN)

KW - WTT-I-1135

KW - WTT-I-1135(EN)

M3 - Report

BT - Site calibration

PB - DTU Wind Energy

ER -

Gómez Arranz P, Georgieva Yankova G. Site calibration. DTU Wind Energy, 2015. 66 p. (DTU Wind Energy WTT I; No. 1135(EN)).