PRACTICAL IMPLICATIONS OF LOCATION-BASED SCHEDULING

  • Niclas Andersson
  • , Knud Christensen

    Research output: Chapter in Book/Report/Conference proceedingArticle in proceedingsResearchpeer-review

    3198 Downloads (Orbit)

    Abstract

    The traditional method for planning, scheduling and controlling activities and resources in construction projects is the CPM-scheduling, which has been the predominant scheduling method since its introduction in the late 1950s. Over the years, CPM has proven to be a very powerful technique for planning, scheduling and controlling projects. However, criticism has been raised on the CPM method, specifically in the case of construction projects, for deficient management of construction work and discontinuous flow of resources. Alternative scheduling techniques, often called repetitive or linear scheduling methods, have proven to be well suited for projects of a repetitive nature, such as building projects. As the repetitive or linear scheduling methods may include locations or places, they are also referred to by the comprehensive term of location-based scheduling (LBS), which is the concept that will be used in this study. LBS is a scheduling method that rests upon the theories of line-of-balance and which uses the graphic representation of a flowline chart. As such, LBS is adapted for planning and management of workflows and, thus, may provide a solution to the identified shortcomings of CPM. Even though LBS has a long history and is well grounded theoretically, it has gained generally little attention in the construction industry. Besides the theoretical research available on LBS, some studies report on the application of LBS, but empirical data on the practical implications of LBS is limited. This study rests upon three case studies of residential projects carried out in Denmark in 2006. The purpose is to test and evaluate the practical implications of LBS when applied on site. The study concludes, with emphasis from the site management involved, that improved schedule overview, establishment of workflows and improved project control constitute the three most important implications of LBS.
    Original languageEnglish
    Title of host publicationCME25:Construction Management and Economics: past, present and future
    PublisherTaylor and Francis Group
    Publication date2007
    Publication statusPublished - 2007
    EventCME 25: Construction Management and Economics: past, present and future - Reading University, Reading, United Kingdom
    Duration: 16 Jul 200718 Jul 2007

    Conference

    ConferenceCME 25: Construction Management and Economics: past, present and future
    LocationReading University
    Country/TerritoryUnited Kingdom
    CityReading
    Period16/07/200718/07/2007

    Cite this