TY - RPRT
T1 - IEA Wind Task 23 Offshore Wind Technology and Deployment. Subtask 1 Experience with Critical Deployment Issues. Final Technical Report
AU - Lemming, Jørgen Kjærgaard
PY - 2010
Y1 - 2010
N2 - The final report for IEA Wind Task 23, Offshore Wind Energy Technology and Deployment, is made up of two separate reports: Subtask 1: Experience with Critical Deployment Issues and Subtask 2: Offshore Code Comparison Collaborative (OC3). The Subtask 1 report included here provides background information and objectives of Task 23. It specifically discusses ecological issues and regulation, electrical system integration and offshore wind, external conditions, and key conclusions for Subtask 1. The Subtask 2 report covers OC3 background information and objectives of the task, OC3 benchmark exercises of aero-elastic offshore wind turbine codes, monopile foundation modeling, tripod support structure modeling, and Phase IV results regarding floating wind turbine modeling.
AB - The final report for IEA Wind Task 23, Offshore Wind Energy Technology and Deployment, is made up of two separate reports: Subtask 1: Experience with Critical Deployment Issues and Subtask 2: Offshore Code Comparison Collaborative (OC3). The Subtask 1 report included here provides background information and objectives of Task 23. It specifically discusses ecological issues and regulation, electrical system integration and offshore wind, external conditions, and key conclusions for Subtask 1. The Subtask 2 report covers OC3 background information and objectives of the task, OC3 benchmark exercises of aero-elastic offshore wind turbine codes, monopile foundation modeling, tripod support structure modeling, and Phase IV results regarding floating wind turbine modeling.
KW - Wind power control and integration
KW - Risø-R-1755
KW - Risø-R-1755(EN)
KW - Vindkraftstyring og integration
M3 - Report
SN - 978-87-550-3860-8
T3 - Denmark. Forskningscenter Risoe. Risoe-R
BT - IEA Wind Task 23 Offshore Wind Technology and Deployment. Subtask 1 Experience with Critical Deployment Issues. Final Technical Report
PB - Danmarks Tekniske Universitet, Risø Nationallaboratoriet for Bæredygtig Energi
CY - Roskilde
ER -