Abstract
The purpose of the paper is to estimate railway project construction cost based on the nominal market price. Currently, estimation of project costs within railway infrastructure procurement is particularly challenging due to; 1) construction costs highly depend on possession timeframes and duration and 2) railway construction work costs are not transparent in the market.
This paper suggests separating the costs into 3 sub-categories: materials, labour and machinery. Evidently, the materials are further broke-down into subcomponents which then remains fixed whereas the cost of labour and machinery are varying depending on the working time possessions presented through the closure of the railway line. The effective working hours, type of construction work and construction speed are used as constraints to ensure the track closure plan remains feasible.
To demonstrate the approach a Danish railway construction project, the new line to the fixed link across Fehmarn Belt, is introduced where it is shown that the non-material cost is about 19% of the total expenditure. By assuming three sets of track blocking scenarios with the same amount of construction works it is proven that given an optimal track closure plan – the overall cost can be decreased by 2.7%. It can be concluded that our approach with an optimal working possession plan can identify the low cost track closures.
This paper suggests separating the costs into 3 sub-categories: materials, labour and machinery. Evidently, the materials are further broke-down into subcomponents which then remains fixed whereas the cost of labour and machinery are varying depending on the working time possessions presented through the closure of the railway line. The effective working hours, type of construction work and construction speed are used as constraints to ensure the track closure plan remains feasible.
To demonstrate the approach a Danish railway construction project, the new line to the fixed link across Fehmarn Belt, is introduced where it is shown that the non-material cost is about 19% of the total expenditure. By assuming three sets of track blocking scenarios with the same amount of construction works it is proven that given an optimal track closure plan – the overall cost can be decreased by 2.7%. It can be concluded that our approach with an optimal working possession plan can identify the low cost track closures.
Original language | English |
---|---|
Publication date | 2014 |
Number of pages | 12 |
Publication status | Published - 2014 |
Event | 14th International Conference on Railway Engineering Design and Optimization - Rome, Italy Duration: 24 Jun 2014 → 26 Jun 2014 Conference number: 14 |
Conference
Conference | 14th International Conference on Railway Engineering Design and Optimization |
---|---|
Number | 14 |
Country/Territory | Italy |
City | Rome |
Period | 24/06/2014 → 26/06/2014 |
Keywords
- cost estimation
- Greenfield-market price
- working possession
- track closure
- phase-based planning
- railway infrastructure project
- construction project planning