Abstract
Estimated and measured relative humidity (RH) change during drying are compared for two concretes, 1: w/c=0.46 and 2: w/(c+0.5fa+2sf)=0.50. The estimations were undertaken by means of the Swedish program TorkaS 1.0. Measurements were performed by RH-sensors type Humi-Guard. Drying of 150 mm thick samples from sides at 60% RH and 22 °C took place from 4 to 56 days after casting. At the end of the drying period the measured RH was about 4% lower than the estimated RH at 1/5th depth from the exposed surface for both concretes. In the middle of the samples, the measured RH of concretes 1 and 2 were 2% lower and 2% higher, respectively, than estimated values.
| Original language | English |
|---|---|
| Title of host publication | Proceedings of Nordic Concrete Research Meeting |
| Publisher | Helli Grafisk AS, Oslo |
| Publication date | 2002 |
| Pages | 283-285 |
| ISBN (Print) | 82-91341-56-7 |
| Publication status | Published - 2002 |
| Event | XVIII Symposium on Nordic Concrete Research - Helsingør, Denmark Duration: 12 Jun 2002 → 14 Jun 2002 Conference number: 18 |
Conference
| Conference | XVIII Symposium on Nordic Concrete Research |
|---|---|
| Number | 18 |
| Country/Territory | Denmark |
| City | Helsingør |
| Period | 12/06/2002 → 14/06/2002 |
Fingerprint
Dive into the research topics of 'Drying of Concrete'. Together they form a unique fingerprint.Cite this
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver