Project Details
Description
Preparation and validation of a simulation model of the CSP (Concentrated Solar Power) plant with biomass heat and power plant and ORC system in Brønderslev. Analyses of measurements from the system in Brønderslev, and calculations with the developed model with the aim to optimize the system design and the control strategy of the plant.
Status | Finished |
---|---|
Effective start/end date | 07/01/2016 → 31/12/2018 |
Collaborative partners
- Technical University of Denmark (lead)
- Aalborg CSP A/S (Project partner)
- Brønderslev Forsyning A/S (Project partner)
- PlanEnergi (Project partner)
Keywords
- Concentrating solar collectors, ORC system, measurements, simulations
Fingerprint